Project update
Night work to pour concrete for guideway
As early as Tuesday, May 26, Sound Transit's contractor will be performing work to pour concrete to assist with the guideway for the Lynnwood Link Extension. The contractor has obtained a Noise…
Project update
On ramp from eastbound SR 104 to Northbound I-5 and off-ramp to westbound SR 104 to be closed
As early as Thursday, May 28, Sound Transit's contractor will begin night work on the ramp from eastbound State Route 104 to the northbound ramp of Interstate 5. Both the on and off ramps will be…
Project update
Work extended: 220th Street SW right turn lane closure and pedestrian detour
As early as Friday, May 15, Sound Transit's contractor will continue work to support a water line installation. The work area is located along the curb near the sidewalk on the south side of 220th…
Project update
On ramp from eastbound SR 104 to northbound I-5 and off-ramp to westbound SR 104 to be closed
As early as Monday, May 11, Sound Transit's contractor will begin night work on the ramp from eastbound State Route 104 to the northbound ramp of Interstate 5. Both the on and off ramps will be…
Project update
Nighttime work along I-5 northbound and southbound lanes
As early as Friday, May 8, Sound Transit's contractor will begin truck hauling and heavy equipment work close to the Mountlake Terrace (MLT) Transit Center. This is to prepare for the Lynnwood Link…
Project update
Weekend closure of Mountlake Terrace parking garage
As early as Friday, May 8, Sound Transit's contractor will close the parking garage at the Mountlake Terrace (MLT) Transit Center in order to prepare for guideway construction of the Lynnwood Link…
Project update
Nighttime work along I-5 Northbound and Southbound lanes
As early as Monday, April 20, Sound Transit’s contractor will begin truck hauling and heavy equipment work close to the Mountlake Terrace (MLT) Transit Center. This is to prepare for link light…
Project update
Postponed until further notice: Weekend Closure of Mountlake Terrace Parking Garage
As early as Friday, April 10, Sound Transit's contractor will close the parking garage at the Mountlake Terrace (MLT) Transit Center in order to prepare for guideway construction of the Lynnwood Link…
Project update
On ramp from eastbound SR 104 to northbound I-5 and off-ramp to westbound SR 104 to close
As early as Monday, April 6, Sound Transit's contractor will begin night work on the ramp from eastbound State Route 104 to the northbound ramp of Interstate 5. Both the on and off ramps will be…
Project update
Nighttime lane closures of southbound I-5 planned near Mountlake Terrace
In order to establish safe work zones for Lynnwood Link Light Rail construction, Sound Transit's contractor will be implementing nighttime traffic controls including the closure of Interstate 5…