Project updates
Learn about where and when construction is happening throughout the ST district.

220th Street SW road closures for night work

Publish Date

As early as Monday, November 16, Sound Transit’s contractor will deliver and set girders across 220th Street SW and north along 60th Ave W. for the Lynnwood Link Extension trackway. All girders will be set from the WSDOT right-of-way, but due to permitting requirements all the work will need to take place at night. This work will be done over a two week period. The contractor has obtained a Temporary Noise Variance to complete the work.

What

Erecting girders (the cross section that goes from column to column to form the trackway).

When

Monday, November 16 through Thursday November 19, 9:00 p.m. – 5:00 a.m.

Where

220th St SW full closure with I-5 southbound on and off-ramp closures (see map). Three night road closure on November 16 through November 18 only. Work will continue north, once the 220th span is complete.

More

  • Uniformed Police Officer will be posted at the intersection of the Northbound I-5 on and off ramps.
  • Large cranes, delivery trucks and aerial lifts will be used during this work.
  • Noise blankets will be used where needed to minimize noise.
  • Plan ahead, leave early and allow extra time to reach your destination.  
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.
Construction map for 220th Street Southwest Detour for Girder setting, Lynnwood Link Extension