46th Ave W/HOV ramps to Lynnwood Transit Center closed

Publish Date

As early as Monday, August 10, Sound Transit’s contractor will be closing the 46th Ave W HOV ramps to the Lynnwood Transit Center. These ramps will be closed for several nights to erect and place girders for the Lynnwood Link Light Rail extension trackway.  This work is weather-dependent and the contractor has obtained a noise variance from the City of Lynnwood. 

What

Erect and place girders (the elements that sit from column to column to form the trackway).

When

Monday, August 10, 9:00 p.m. – Thursday, August 13, 5:00 a.m.
Monday, August 17, 9:00 p.m. – Thursday, August 20, 5:00 a.m.

Where

46th Ave W HOV lanes from I-5 North and Southbound exits. 46th Ave W HOV on-ramp to I-5 (see map). 

More

•    Equipment used: cranes, forklifts, loaders and large delivery trucks.
•    Flaggers will be present.
•    Plan ahead, leave early and allow extra time to reach your destination.  

Construction map of 46th Ave HOV ramp closure