Closure of 212th Street SW for night work
Publish Date
As early as Thursday, November 12, Sound Transit’s contractor will close 212th Street SW to deliver and set girders for the Lynnwood Link Extension trackway. This work will include large trucks hauling material, and cranes to install the girders. The contractor has obtained a noise variance to complete this work.
What
Erecting girders (the cross section that goes from column to column to form the trackway).
When
Thursday, November 12, and Saturday, November 14, 9:00 pm – 5:00 am.
Where
Work will take place along 212th St SW, west of 52nd Ave intersection between 54th Ave W and the I-5 overpass. There will be a detour in place (see map).
More:
- Noise blankets will be used where needed to help minimize noise.
- Flaggers will be present.
- Due to inclement weather or unforeseen issues, dates and times are subject to change.