Project updates
Learn about where and when construction is happening throughout the ST district.

Night work at Mountlake Terrace Transit Center

Publish Date

Overnight Monday, June 7 through Thursday, June 10 from 10 p.m. to 7 a.m., Sound Transit’s contractor will continue to work at night at the Mountlake Terrace Transit Center (MLT TC) to build the Lynnwood Link guideway. The parking garage will remain open. This work will be done at night. The contractor has obtained a noise variance to complete this work.

What

Night work to continue to build the Lynwood Link guideway.

When

Overnight Monday, June 7 – Thursday, June 10, from 10 p.m. to 7 a.m.

Where

MLT TC bus loop. Trucks will come in and back into the work area from the bus loop to unload the girders.

More

  • Equipment to be used will be cranes, trucks, forklifts and manlifts.
  • Flaggers will be present.
  • Plan ahead, leave early and allow extra time to reach your destination.  
Construction map for Mountlake Terrace Girder work June 2021, Mountlake Terrace Station