Scriber Creek Trestle Installation

Publish Date

As early as Monday, August 31st, Sound Transit’s contractor will begin night work to install the Scriber Creek Trestle. Crews will use hand tools and welding to complete this work. The contractor has obtained a noise variance to complete the trestle installation. 

What

Night work will begin next week to prepare for the trestle, which is a temporary horizontal support to help build the trackway for the Lynnwood Link Extension. This trestle will be in place for two years while the trackway is completed. After which it will be removed.

When

Monday, August 31st – Wednesday, September, 30th 7:00 p.m. to 7:00 a.m. (Monday – Thursday night work only).  

Where

Scriber Creek Trail between Interurban Trail and 200th Street SW (see map).

More:

•    Crews will maintain a safe and secure work zone. 

Scriber Creek Trestle Installation construction map