Seattle City Light work for drilled shafts
Publish Date
As early as Monday, June 8, Seattle City Light (SCL) will assist Sound Transit's contractor with work that will support the construction of the guideway for the Lynnwood Link Extension. The SCL work will take place in the daytime.
Sound Transit's contractor is currently working at night drilling shafts.
What
De-energizing a transmission line. Power to homes will not be affected.
When
Monday, June 8 and Monday, June 15. 7 a.m. to 3 p.m.
Where
The end of Northeast 200th Street near 12th Avenue Northeast.
More
- SCL will utilize a crane.
- Flaggers will be present.
- You may hear back-up alarms from the SCL trucks and bull horns during the day.
- Plan ahead, leave early and allow extra time to reach your destination.
- Due to inclement weather or unforeseen issues, dates and times are subject to change.