Daily full road closure of 46th Ave W

As early as Friday, June 21, Sound Transit’s contractor will continue working on the storm crossing at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW. Detours will be…

Canceled: Full closure of 46th Ave W

*Update: This work has been pushed back and it will no longer take place this week. We will send out another alert when this work is rescheduled.As early as Wednesday, June 12, Sound Transit’s…

Full closure of 48th Ave W

As early as Monday, June 10, Sound Transit’s contractor will continue work on the traffic signal on 200th St SW. This work will require the closure of 48th Ave W north of 200th St SW. We will…

Full closure of 46th Ave W

As early as Monday, June 10, Sound Transit’s contractor will continue working on pavement markings at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW and the HOV ramp…

Full closure of 48th Ave W

As early as Thursday, June 6, Sound Transit’s contractor will finish installing a utility crossing on 48th Ave W. This requires the closure of 48th Ave W south of 200th St SW. We will maintain access…

Full closure of 48th Ave W

As early as Tuesday, June 4, Sound Transit’s contractor will finish utility crossings on 200th St SW. This work will require the closure of 48th Ave W north of 200th St SW. We will maintain access to…

Center lane closure on 44th Ave W

As early as Monday, June 3, Sound Transit’s contractor will continue work on 44th Ave W for median demolition and road paving. This work will require crews to close the center lane on southbound 44th…

Full closure of 46th Ave W

As early as Monday, May 20, Sound Transit’s contractor will continue working on utilities at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW. Detours will be provided (…

Center lane closure on 44th Ave W

Starting Monday, May 13, Sound Transit’s contractor will begin median demolition and paving on 44th Ave W. This will require closing the center lane on 44th Ave W, just south of 200th St SW. Detours…

Full closure of 46th Ave W

As early as Monday, May 13, Sound Transit’s contractor will continue working on utilities at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW. Detours will be provided (…