Project update
Nightly lane restrictions on NE 145th St (WA-523)
From Saturday, Aug. 17, through Thursday, Aug. 22, Sound Transit will conduct waterline work on eastbound and westbound NE 145th St (WA-523) from 3rd Ave NE to 8th Ave NE. This work will cause…
Project update
Full nightly closures of 200th St SW
As early as Friday, Aug. 16, Sound Transit’s contractor will continue road work on 200th St SW for paint striping. This will require two separate nighttime closures of 200th St SW between 50th Ave W…
Project update
Night closure of right lanes on NE Northgate Way
As early as Monday, Aug. 12, Sound Transit will be restricting the eastbound and westbound right lanes of NE Northgate Way between Corliss Ave N and 1st Ave NE for electrical work. These closures are…
Project update
Correction: Nightly lane restrictions on NE 175th St and King County Metro ramp closures
As early as Monday, Aug. 12, Sound Transit will close the King County Metro northbound I-5 off- and on-ramp to NE 175th St, northbound I-5 off-ramp to NE 175th St, and the right lanes of eastbound…
Project update
Nightly closure of northbound I-5 right lane and on-ramp from NE 175th St
Starting Monday, Aug. 12, Sound Transit will close the northbound I-5 right lanes and on-ramp from NE 175th St and off-ramp to NE 205th St for barrier work striping. This work is part of…
Project update
Center lane closure on 44th Ave W
Starting Monday, Aug. 12, Sound Transit’s contractor will continue median demo and road paving on 44th Ave W. This work will require crews to close the center lane on southbound 44th Ave W, north of…
Project update
Nightly full closure of 236th St SW
Starting Wednesday, Aug. 7, Sound Transit’s contractor will continue mill and overlay work on 236th St SW in Mountlake Terrace. This work will require closing the street at night…
Project update
Center lane closure on 44th Ave W
Starting Monday, Aug. 5, Sound Transit’s contractor will continue road work on 44th Ave W. This will require closing the center turn lane just south of 200th St SW. Detours for the left turn…
Project update
Full nighttime road closure of 5th Ave NE from NE 145th St to NE 148th St
Starting Monday, Aug. 5, Sound Transit crews will finish paint striping on 5th Ave NE from NE 145th St to NE 148th St, resulting in nighttime road closures. The NE 145th St to northbound I-5 on-ramp…
Project update
Daily full road closure of 46th Ave W
As early as Monday, Aug. 5, Sound Transit’s contractor will continue grinding and paving work on 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW. Detours will…