Project update
Alternating lane closure at 5th Ave Northeast from 145th to NE 148th Street for night work
As early as Monday, June 13th, Sound Transit will begin closing the northbound lane on 5th Ave from NE 145th Street to NE 148th Street for utility work. Crews will later shift and close the…
Project update
Northbound lane closure at 5th Ave Northeast from 145th to NE 148th Street for night work
As early as Monday, June 6th, Sound Transit will begin closing the northbound lane on 5th Ave from NE 145th Street to NE 148th Street for utility work. This work is part of the future Lynnwood Link…
Project update
Night closure at NE 155th Street from 1st Ave NE to 3rd Ave NE, next to Shoreline Fire Department
Starting Sunday, June 5th, Sound Transit will be performing nightly road closures of NE 155th St. from 1st Ave NE to 3rd Ave NE, next to the Shoreline Fire Dept. The work is performed at night to…
Project update
Parking lot shifts at Lynnwood Transit Center (LTC)
As early as June 13, Sound Transit’s contractor will close off sections of the Lynnwood Transit Center parking lot for continued construction activities to complete the improvements for the Lynnwood…
Project update
Night closure at 1st Ave NE between NE 103rd Street to Northgate Way with additional ramp closures
On Thursday, June 2nd, Sound Transit's contractor will be closing 1st Ave. between NE 103rd Street and Northgate Way and both on/off ramps to mobilize equipment for the Lynnwood Link Extension light…
Project update
Westbound Right Lane Closure of 236th St SW
From Monday, May 30 to Friday, September 2, Sound Transit’s contractor will work at 236th St SW westbound between the on-ramp to I-5 southbound and 59th Pl W for installation of a retaining wall and…
Project update
Off-Ramp night closure at Northbound Interstate-5 to Northeast 145th Street Exit 175
Tuesday, May 31st, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for construction of the Lynnwood Link light rail.
Project update
Nightly Closure of 236th St SW
From Monday, May 23 to Thursday, June 2, from 11 p.m. to 5 a.m., excluding Fridays and weekends, Sound Transit’s contractor will work at 236th St SW between the on-ramp to I-5 southbound and 59th Pl…
News release
Closure of northbound I-5 highway and ramps at Mountlake Terrace scheduled overnight for May 20-22
Crews working on the Lynnwood Link Extension will be closing the northbound lanes of I-5 between State Route 104 and 220th Avenue SW in Mountlake Terrace (MLT) overnight starting on Friday, May 20…
Project update
Night closure at 1st Ave NE between NE 103rd Street to Northgate Way with additional ramp closures
Beginning Wednesday, May 25th, Sound Transit's contractor will be closing 1st Avenue between Northeast 103rd Street to Northgate Way and both on/off ramps to mobilize equipment for the Lynnwood Link…