Nightly Closure of 44th Ave W

From Tuesday, February 22 to Saturday, February 26, Sound Transit’s contractor will work at night at 44th Ave W. There will be closures on 44th Ave W and the on-ramp to I-5 southbound to remove…

Night time road closure on 5th Ave NE and NE 130th Street overpass and off-ramp

As early as February 22nd, Sound Transit’s contractors will work on 5th Ave NE and NE 130th Street overpass and off-ramp for guideway construction as part of the future link light rail.

One lane road with alternating traffic on Northeast 155th Street between 1st Ave NE to 2nd Ave NE

Monday, February 21st, Sound Transit will be working on NE 155th St. of Interstate-5 underpass. This work is part of Sound Transit’s Lynnwood Link Extension Project.

5th Ave NE lane shifts at NE 148th Street

As early as February 14th, Sound Transit’s contractors will work on 5th Ave NE and NE 148th Street for utility work as part of the future link light rail.

Night time road closure on 5th Ave NE and NE 130th Street overpass and off-ramp

As early as February 16th, Sound Transit’s contractors will work on 5th Ave NE and NE 130th Street overpass and off-ramp for guideway construction as part of the future link light rail.

Nightly Closure Along 48th Ave W

From Monday, February 14 to Thursday, February 24, Sound Transit’s contractor will work at night at 48th Ave W. The thru road between 46th Ave W and 48th Ave W will be closed during work hours to…

Extended full closure at NE 145th overcrossing and NB I-5 NE 145th Street exit 175

As early as Monday, February 14th, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for work zone for girder setting. Additionally, there will be a full closure at the NE 145th…

1st Ave NE road closure between NE 103rd Street to Northgate Way for night workramp for guideway construction.

As early as Wednesday, February 9th, Sound Transit’s contractor will close 1st Ave NE between NE 103rd Street to Northgate Way to continue construction for the Lynnwood Link Extension guideway.

Night closure at 1st Ave NE at Northgate Way Intersection and NB I-5 Northgate Way on-ramp for guideway construction.

As early as Monday, February 7th, Sound Transit will be closing 1st Ave NE at Northgate Way Intersection and I-5 Northbound on-ramp at Northgate Way. The night time closure will be utilized to…

Extended lane restrictions work on NE 145th St (WA-532) from 3rd Ave NE to 8th Ave NE

This work has been extended to February 4th. Sound Transit will continue night lane restrictions on both Eastbound & Westbound directions of NE 145th St (WA-532) from 3rd Ave NE to 8th Ave NE.…