Night closure at 1st Ave NE Northgate Way intersection and northbound I-5 Northgate Way on-ramp for guideway construction

As early as Monday, Dec. 13th, Sound Transit will be closing 1st Avenue Northeast Northgate Way Intersection and Interstate 5 northbound on-ramp at Northgate Way. The nighttime closure will be…

Night work along the I-5 and State Route 104 Interchange through December

Through the month of December, Sound Transit’s contractor will work at night along the I-5 and the SR 104 Interchange in Shoreline to complete concrete pours for the elevated guideway for the future…

Night road closures at of Westbound & Eastbound NE 175th Street

Monday, December 6th, Sound Transit will be closing NE 175th Street to Northbound and Southbound I-5 on-ramp. The closure will be utilized for guideway construction as part of the Lynnwood Link…

Off-ramp night closure at northbound I-5 to NE 145th St Exit 175

Beginning Monday, Dec. 13th, Sound Transit will be closing the off-ramp from northbound Interstate 5 via exit 175 for construction of the Lynnwood Link light rail.

Night closure at 1st Ave NE at Northgate Way Intersection and NB I-5 Northgate Way on-ramp for guideway construction

As early as Tuesday, December 7th, Sound Transit will be closing 1st Ave NE at Northgate Way Intersection and I-5 Northbound on-ramp at Northgate Way. The night time closure will be utilized to…

Sound Transit seeks public input on transit-oriented development in Lynnwood

Sound Transit is currently asking the public to participate in an online survey to share community priorities on future transit-oriented development in Lynnwood. The agency owns land next to the…

Share your priorities for Lynnwood City Center transit-oriented development

Sound Transit owns land next to the future Lynnwood City Center Station that will be available for development after we complete Link light rail construction.

Extended night closures at 1st Ave NE between Northgate Way and NE 103rd Street; NE 107th ramp closures

This work is being extended to December 2nd. Sound Transit will be closing lanes at 1st Ave NE between Northgate Way and NE 103rd Street. In addition, both NE 107th on-ramp and off-ramp will be…

Extended full closure at NE 145th overcrossing and NB I-5 NE 145th Street exit 175

This work is being extended to December 2nd. Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for work zone for girder setting. Additionally, there will be a full closure at the NE…

Construction of Lynnwood Link extension reaches fifty percent completion

Two years after groundbreaking on the project, civil construction on the Lynnwood Link extension has reached the fifty percent completion mark. Construction teams continue to advance the work on the…