Project update
Full night time road closures at NE 175th Street
Starting Monday, April 11th, Sound Transit will be closing both directions of NE 175th Street from 5th Ave NE to the I-5 underpass, including the closure of both NE 175th Street to Northbound I-5 on…
Project update
Signal shutoff at 236th St SW and I-5 NB off-ramp
As early as Monday, April 4, Sound Transit’s contractor will shut down the traffic signals at the intersection of 236th St SW and the I-5 Northbound off-ramp from 7 AM – 12 PM. There will be a…
Project update
Closure of Mountlake Terrace Parking Garage Lower Entrance
As early as Monday, March 28, Sound Transit’s contractor will close the lower (main) entrance to the parking garage at the Mountlake Terrace (MLT) Transit Center in order to install a retaining wall…
Project update
Nightly Closure of 236th St SW
As early as Monday, March 28 to Thursday, March 31, Sound Transit’s contractor will work at 236th St SW between the on-ramp to I-5 southbound and 59th Pl W for installation of utilities from 11 p.m.…
Project update
Night work along the I-5 and State Route 104 Interchange through April
Starting March 28 through April 28, Monday - Thursday, Sound Transit’s contractor will work at night along the I-5 and SR 104 Interchange in Shoreline to complete concrete pours for the elevated…
Project update
Nightly Closure of 236th St SW
From Monday, March 14 to Thursday, March 17, Sound Transit’s contractor will work at 236th St SW between the on-ramp to I-5 southbound and 59th Pl W for installation of utilities from 11 PM to 5 AM.
Project update
Nightly Closure of 236th St SW
From Monday, March 7 to Thursday, March 10, Sound Transit’s contractor will work at 236th St SW between the on-ramp to I-5 southbound and 59th Pl W for installation of utilities from 11 PM to 5 AM.
Project update
Westbound & Eastbound night road closures on NE 175th Street
Thursday, March 3rd, Sound Transit will be performing directional road closures at NE 175th Street from 5th Ave NE to the I-5 underpass. The closure will be utilized for guideway construction as part…
Project update
Nighttime Mountlake Terrace Garage entrance closure
From Monday, Jan. 24 to Thursday, Jan. 27, Sound Transit's contractor will work at night at the entrance to the Mountlake Terrace Garage.
Project update
Full nighttime road closures at NE 175th Street
Starting Monday, Jan. 3rd, Sound Transit will be closing both directions of Northeast 175th Street from 5th Avenue Northeast to the Interstate 5 overpass, including the closure of both Northeast…