Night closure of 1st Avenue NE and northbound I-5 on-ramp and off-ramp at NE 107th Street

As early as Monday, July 31, Sound Transit will close northbound I-5 on-ramp and off-ramp at NE 107th Street as a part of the Lynnwood Link Extension project.

All-day work at NE 130th Street Station Garage

On Monday, June 19, contractors will be working on the Sound Transit guideway at the NE 130th Station Garage as a part of the Lynnwood Link Extension.

Night closures of northbound I-5 right lanes and off-ramp at NE 145th St.

Starting as early as Tuesday, June 6, Sound Transit will be performing northbound I-5 right lane closure from NE 130th St. to NE 145th St. The northbound I-5 off-ramp to NE 145th St will be closed.…

Night closure of northbound I-5 on-ramp at Northgate Way and off-ramp to NE 130th St.

As early as Monday, June 5, Sound Transit will close the Northgate Way northbound I-5 on-ramp, including the northbound I-5 right lane and the northbound I-5 off-ramp to NE 130th St. Crews will be…

NE 130th St Infill Station design approaches final approvals, with station finishes construction to begin in fall 2023

Current construction at NE 130th St Infill Station is focused on the concrete platform and canopy structural steel. This work will be completed prior to electrification of the Lynnwood Link Extension…

NE 130th Street Infill Station Updates

Early construction and project final design progress — NE 130th Street Station on schedule for mid-2026 opening Last year, the Sound Transit Board of Directors acted to ensure our voter-approved…

Night time road closure on 5th Ave NE and NE 130th Street overpass and off-ramp

As early as Nov. 2nd, Sound Transit's contractors will work on 5th Avenue Northeast and Northeast 130th Street overpass and off-ramp for guideway construction as part of the future link light rail.

Night time closure at NE 130th off-ramp from northbound I-5

As early as Sunday, Nov. 1st, Sound Transit will close the Northeast 130th Street off-ramp from northbound Interstate 5 for guideway construction. Additionally, 5th Avenue will be closed from…

Project timeline and update

A reminder to our stakeholders that we will go in front of Board of Directors for the Oct. 28th meeting to review a portion of the NE 130th Infill station schedule in order to keep this project in…

Night time closure at NE 130th off-ramp from Northbound I-5

As early as Sunday, October 17th, Sound Transit will close the NE 130th Street off-ramp from NB I-5 for guideway construction.