Operations and Maintenance Facility South
Maintaining the growing light rail fleet.

Timeline and milestones

  • Voter approval (2016)

  • MilestoneTarget
    Alternatives development2018 - 2019
    Board identifies sites for further study in the Draft Environmental Impact Statement2019
    Draft Environmental Impact Statement2019 - 2021
    Board identifies a preferred site alternative2021
    Final Environmental Impact Statement2024
    Board selects project to be built2024
  • Milestone
    Final facility design
    Procure and commission facility and public art
    Obtain land use and construction permits
    Property acquisition/relocation
    Groundbreaking
    Construction updates and mitigation
    Safety education
    Testing and pre-operations
  • Open for operations (2029*)

* The Board has identified a target in-service date of 2029. The agency is working to accelerate the current schedule to achieve that date.