Voter approval (2016)
-
Milestone Target Alternatives development 2018 - 2019 Board identifies sites for further study in the Draft Environmental Impact Statement 2019 Draft Environmental Impact Statement 2019 - 2021 Board identifies a preferred site alternative 2021 Final Environmental Impact Statement 2024 Board selects project to be built 2024 -
Milestone Final facility design Procure and commission facility and public art Obtain land use and construction permits Property acquisition/relocation Groundbreaking Construction updates and mitigation Safety education Testing and pre-operations -
Open for operations (2029*)
* The Board has identified a target in-service date of 2029. The agency is working to accelerate the current schedule to achieve that date.