Project update
Ronald water waste line relocation at 1st Avenue Northeast at 174th Street
Starting Aug. 5th, Sound Transit will closed 1st Avenue Northeast at 174th Street to work on the utility relocation. Sound Transit will be relocating the Ronald water waste line in order to construct…
Project update
Interstate 5 northbound striping at 175th Street to State Route 104
Starting Wednesday, Aug. 7th, Sound Transit will be re-striping northbound Interstate 5 from 175th Street to State Route 104, to widen the construction work zone on the shoulder of the freeway. What…
Project update
5th Avenue Northeast closure, Seattle
5th Avenue Northeast roadway between Northeast 125th Street and Northeast 145th Street, along Jackson Golf Course, will close August 12th so Sound Transit crews can begin construction of the elevated…
Project update
5th Avenue Northeast closure, Seattle
5th Avenue Northeast roadway between Northeast 125th Street and Northeast 145th Street, along Jackson Golf Course, will close so Sound Transit crews can begin construction of the elevated guideway…
Project update
Steel pole foundation work on 5th Avenue Northeast
Starting as early as July 15th, Sound Transit will close 5th Avenue Northeast to a full lane closure from Northeast 180th Street to Northeast 185th Street as part of the Lynnwood Link Extension early…
Project update
Steel pole foundation work on Northeast 180th Street
Starting as early as July 8th, Sound Transit will be working on Northeast 180th Street. Sound Transit will be working on setting steel pole foundations for early work construction to relocate…
Project update
Steel pole foundation work on Northeast 185th Street
Starting as early as June 27th, Sound Transit will reduce Northeast 185th Street to a two lane road going each direction. Sound Transit will be working on setting steel pole foundations for early…