Project update
In this alert: Weekday construction traffic impacts, Upcoming weekend ramp closures, Early morning concrete pours, and reminder of ongoing closures.
Weekday construction traffic impacts: Week of March 5-9 I-90 Monday, 5 a.m. to Thursday 3 p.m.: Over the next two weeks, the Bellevue Way Southeast to I-90 west HOV ramp will be closed from 5 a.m.…
Project update
In this alert: Upcoming weekend ramp closures, Weekday construction traffic impacts, Enatai Park-and-Ride one-day closure, Early morning concrete pours and reminder of ongoing closures
Weekend of Feb. 24-25 and March 10-11, three ramps from I-90 to Bellevue Way SE closed Crews will continue work on drilled shafts adjacent to the I-90 ramps and Southeast 30th. Sound Transit's…
Project update
Night closures on I-405 in Bellevue on Feb. 26 – Mar 15
Overnight drivers should be aware of upcoming lane closures in downtown Bellevue in preparation for construction of the elevated light rail structure across I-405. Sound Transit's contractor will be…
Project update
Enatai Park-and-Ride one-day closure
The Enatai Park-and-Ride will be closed Friday, Feb. 23rd for maintenance. During the closure, commuters are encouraged to use a recently opened park-and-ride located at Bellevue Church of Christ…
Project update
In this alert: Weekday construction traffic impacts, Upcoming weekend ramp closures, Suspended work platform installation, Enatai park-and-ride one-day closure, Early morning concrete pours, and Reminder of ongoing closures
Weekday construction traffic impacts: Week of Feb. 19-23 112th Avenue Southeast Monday-Friday 9 a.m. to 4 p.m.: Daily closures of one northbound lane of 112th Avenue Southeast, between Bellevue Way…
Project update
In this alert: Weekday construction traffic impacts, Access changes at Surrey Downs Park, Clearing and vegetation removal along 112th Ave SE, Early morning work at I-90 in Bellevue, and Reminder of ongoing closures
Weekday construction traffic impacts: Week of Feb. 12-16 I-90 Ramps Monday-Friday 8 p.m. to 3 p.m.: Daily/overnight closure of the Bellevue Way Southeast to I-90 west HOV ramp. The duration of…
Project update
In this alert: Weekday construction traffic impacts, Waterline leak detection and CCTV inspection, Early morning concrete pours, Reminder of ongoing closures
Weekday construction traffic impacts: Week of Feb. 5-9 I-90 Ramps Monday-Friday 8 p.m. to 3 p.m.: Daily/overnight closure of the Bellevue Way Southeast to I-90 west HOV ramp. The duration of these…
Project update
In this alert: Weekday construction traffic impacts, Century Link work, Early morning concrete pours, and reminder of ongoing closures.
Weekday Construction traffic impacts: Week of January 29-February 2 I-90 Ramps Monday-Friday 8 p.m. to 3 p.m.: Daily/overnight closure of the Bellevue Way SE to I-90 west HOV ramp. The duration of…
Project update
In this alert: Reminder of weekend ramp closures, Weekday construction traffic impacts, Early morning concrete pours and nighttime light pole installation, Weekend of January 20-21, and reminder of ongoing closures
This closure will be repeated overnight on Wednesday and Thursday, Jan. 24-25 from 9 p.m. to 5 a.m. Crews will continue work on drilled shafts adjacent to the I-90 ramps and Southeast 30th. Sound…
Project update
In this alert: Weekday construction traffic impacts, Early morning concrete pour, Wednesday, January 18, Weekend of January 20-21, and reminder of ongoing closures
Weekday construction traffic impacts: Week of Jan. 16-19 No work in roadway on Monday, Jan. 15th due to observance of Dr. Martin Luther King Holiday. Tuesday-Friday 8 p.m. to 3 p.m.: Daily/…