South Bellevue Station
South Bellevue Park-and-Ride, room for 1,500 cars.

News and updates

Upcoming construction traffic impacts 112th Ave. SE and SE 8th St. intersection modification

As progress continues on the road-over-rail portion of East Link, crews will begin constructing the guideway on the west side of 112th Ave SE near SE 8th St. In order to safely perform the work,…

***UPDATED SCHEDULE DUE TO WEATHER IMPACTS*** I-405 to westbound I-90 overnight ramp closures and lane reductions on westbound I-90

What This work was scheduled for an earlier date, but was postponed due to snow and ice.  Work continues on the cast-in-place long span rail bridge over I-90. Crews plan to close all ramps from…

Upcoming construction traffic impacts Thursday, Feb. 14 – Friday, Feb. 22

UPDATED 2/14/2019: This activity has been postponed to Monday, Feb. 18th due to weather. What Work continues on the cast-in-place long span rail bridge over I-90. Crews plan to close all ramps from…

Upcoming construction traffic impacts Monday, February 4-Friday, February 8

UPDATED 2/6/2019: This activity has been postponed until further notice due to weather. A new schedule will be included in a future alert. What Work continues on the cast-in-place long span rail…

Weekend full closure of Bellevue Way Southeast and ramps to/from Bellevue Way Southeast: Jan. 26-27

In order to install new storm drain line under Bellevue Way Southeast and set precast concrete girders adjacent to Bellevue Way Southeast, Sound Transit's contractor plans to close all lanes of…

Lane reductions and nighttime work on Bellevue Way Southeast

Crews working to build Sound Transit's East Link project in south Bellevue will install the final sets of precast concrete girders during the weeks of Jan. 21 and Jan. 28. Lane and ramp closures will…

Northbound lane closure: 112th Avenue Southeast between Bellevue Way Southeast and Southeast 8th Street

This alert includes an updated description and map which reflect the detour north bound drivers should use during this work. All other information was correct. We apologize for any inconvenience.…

Weekly construction traffic impacts and ongoing closures Monday, Jan. 7 – Friday, Jan. 11

I-90 Bike trail and 108th Avenue Southeast Monday-Friday 8:30 a.m. to 3:30 p.m., as needed: To prepare for restoration following installation…

Weekly construction traffic impacts and ongoing closures Wednesday, Jan. 2 – Friday, Jan. 4

Bellevue Way SE Work to construct the East Link guideway adjacent to Bellevue Way SE will continue in 2019. In order to work in the eastside curb lane while maintaining two lanes of traffic in the…

Bellevue Way SE