-
Voter approval (2016)
-
Milestone Target Alternatives development Board identifies preferred and other Draft EIS alternatives Draft Environmental Impact Statement Board confirms or modifies the Preferred Alternative Final Environmental Impact Statement Board selects project to be built Federal Record of Decision 2024 -
WSLE is scheduled to begin design after the Federal Record of Decision.
Milestone Final route design Final station designs Procure and commission station and public art Obtain land use and construction permits Property acquisition/relocation -
WSLE is scheduled to begin construction and testing in 2027, and will conclude in 2032. See below for more information.
Milestone Groundbreaking Construction updates and mitigation Safety education Testing and pre-operations -
Start of service, 2032
West Seattle Link Extension
Serving regional jobs, dense neighborhoods