77th Ave Sidewalk Closure for Plaza Construction

Publish Date

Beginning as early as Monday, July 22, work will begin on the 77th Ave SE entrance plaza as crews install new utilities, sidewalks, landscaping and other finishes. To safely complete this work, the sidewalk along 77th Ave between Sunset Highway and North Mercer Way, will close for approximately eight weeks. Pedestrians will be detoured to 80th Ave. SE during this time.

What

Plaza construction at the 77th Ave SE station entrance, between Sunset Highway and North Mercer Way.

When

Beginning as early as Monday July 22, for approximately eight weeks.

Where

77th Ave SE, between Sunset Highway and North Mercer Way.

More

  • The sidewalk along 77th Ave SE, between Sunset Highway and North Mercer Way, will close for approximately eight weeks to accommodate entrance plaza construction.
  • Pedestrians will be detoured to 80th Ave. SE during this time. Please follow directional signage to safely access your destination. 
  • Work will occur Monday – Friday, 7 a.m. – 3 p.m. Crews will install utilities, sidewalks, landscaping and other finishes.
  • Plan ahead, leave early and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.
Mercer Island work area, beginning July 22