Weekday construction traffic impacts: Morning of March 21 and week of March 26-30

I-90 (overnight/morning work tonight)

Wednesday, March 22nd and Tuesday, March 27th: Early morning ramp closure of the westbound I-90 to northbound Bellevue Way SE ramp. Wednesday morning, from 2 a.m. - 5 a.m., ramps from westbound I-90 to northbound Bellevue Way SE will be closed while Sound Transit’s contractor delivers and removes materials to the work site. This closure will be repeated the morning of Wednesday, March 27th.

During the overnight closure, all lanes of Bellevue Way SE will remain open and drivers traveling southbound on Bellevue Way SE will continue to have access to eastbound and westbound I-90. Detour to Bellevue Way SE via I-405, using the SE 8th Street exit to southbound 112th Avenue SE.

112th Avenue SE

Monday-Friday 9 a.m. to 4 p.m.: As needed, In order to complete utility crossings between Main Street and SE 6th Street, crews will alternate the sidewalk between the east and west side of 112th Avenue SE. Signed detours will be in place for pedestrians and bicyclists.

Monday-Friday 9 a.m. to 4 p.m.: Daily closures of one northbound lane of 112th Avenue SE, between Bellevue Way SE and Main Street.

Monday-Friday 7 a.m. to 3 p.m.: As needed, in order to complete utility work and facilitate wall construction, Sound Transit’s contractor may close one southbound lane of 112th Avenue SE, between SE 8th Street and Bellevue Way SE.

Monday-Friday 9 a.m. to 4 p.m.: Daily closures of one southbound lane of 112th Avenue SE, between Main Street and SE 8th Street.

Bellevue Way SE

Monday-Friday 10 a.m. to 8 p.m.: Daily closures of one northbound lane of Bellevue Way SE, between the South Bellevue Station site and the Wye at 112th Avenue SE.

Monday-Friday 6 a.m. to 2 p.m.: As needed, crews will close one southbound lane of Bellevue Way SE, between the Wye at 112th Avenue SE and SE 30th.

Early morning work at I-90 in Bellevue

Crews plan to begin work between east and westbound I-90 as early as 4 a.m. Monday-Friday, March 26th-30th.

In order to complete necessary work and reopen the Bellevue Way Southeast to I-90 west HOV ramp by 3 p.m. each day, crews need to begin work earlier. Crews will minimize noisier activities to normal working hours, M-F 7 a.m. to 6 p.m. and equipment/vehicles will utilize broadband backup alarms. Sound Transit's contractor is permitted to work expanded hours along Bellevue Way Southeast, including 24-hour work in the area south of the future South Bellevue Station site.

Reminder of ongoing closures

For information on previously announced long-term and ongoing closures click here.

  • Daily/overnight closure of the Bellevue Way Southeast to I-90 west HOV ramp
  • Sidewalk closures and detours on Bellevue Way Southeast and 112th Avenue Southeast
  • Closure of Southeast 15th at 112th Avenue Southeast
  • Winters House and Blueberry Farm Closure and new temporary lot