Project updates
Learn about where and when construction is happening throughout the ST district.

Progress continues at the Judkins Park Station

Publish Date
Body

Having demolished one of the I-90 bridges that crossed Rainier Ave. in October, construction at the Judkins Park Station continues to progress. Since October, crews have demolished and excavated the site; have begun to form and pour concrete walls for the station’s east entrance and platform; and have completed rail welding. In the coming months, the station’s entrances and platform will continue to take shape. Check out recent photos of construction progress below. 

Image of crewmember with welding machine at Judkins Park Station East Link Extension

A crewmember lines up the rail welding machine to join two 80-foot ‘sticks’ together. All rail required for the I-90 East Link segment has been delivered and welded.

Image of steel supports and concrete forms for station walls at Judkins Park, East Link Extension
Steel supports hold wood falsework forms for the station’s concrete walls (left). Concrete is then poured, cured and the wood forms removed to build the station’s walls (right).
Image of elevator shaft concrete form and rendering of station entrance at Judkins Park, East Link Extension
Crewmembers pour concrete to form the elevator shaft at the 23rd Ave. station entrance (left). A rendering of the completed entrance when trains roll in 2023 (right).

 

Image of demolition, excavation and rendering of station entrance at Judkins Park Station, East Link Extension
Demolition and excavation for the entrance on the west side of Rainier Ave (left) and a rendering of the completed entrance (right).