-
Voter approval (2016)
-
Milestone Target Alternatives development Board identifies preferred and other Draft EIS alternatives Draft Environmental Impact Statement Final Environmental Impact Statement Federal Record of Decision Alignment and station concept refinements Board selects project to be built -
Milestone Target Preliminary engineering Board authorizes properties to be acquired for project Select design-build contractor Complete design and acquire permits 2019 - 2022 -
Milestone Target Survey, test shafts geotechnical investigations 2019 Tree removal, guideway, station and garage construction, system installation 2020 - 2023 Final restoration and landscaping, systems testing 2023 -
Open for service (2025)*
Downtown Redmond Link Extension
Serving Marymoor Park and Redmond Town Center