Downtown Redmond Link Extension
Serving Marymoor Park and Redmond Town Center

Timeline and milestones

  • Voter approval (2016)

  • MilestoneTarget
    Alternatives development

     

    Board identifies preferred and other Draft EIS alternatives

     

    Draft Environmental Impact Statement

     

    Final Environmental Impact Statement

     

    Federal Record of Decision

     

    Alignment and station concept refinements

     

    Board selects project to be built

     

  • MilestoneTarget
    Preliminary engineering

     

    Board authorizes properties to be acquired for project

     

    Select design-build contractor

     

    Complete design and acquire permits2019 - 2022
  • MilestoneTarget
    Survey, test shafts geotechnical investigations2019
    Tree removal, guideway, station and garage construction, system installation2020 - 2023
    Final restoration and landscaping, systems testing2023
  • Open for service (2025)