Project update
Closure of Alderwood Mall Blvd
As early as Friday, April 5, Sound Transit’s contractor will continue road work on Alderwood Mall Blvd. This will require the full closure of Alderwood Mall Blvd east of 44th Ave W. Detours will be…
Project update
Full daytime closure of 200th St SW
As early as Wednesday, April 3, Sound Transit’s contractor will continue road work on 200th St SW for mast arm installation for the traffic signals. This will require the full closure of 200th St SW…
Project update
Parking and paratransit/ADA drop-off opening at Lynnwood Transit Center
As early as Saturday, March 30, the parking lot south of the bus loop at the Lynnwood Transit Center will be open to the public for parking and paratransit/ADA drop-off. The bus layover area will be…
Project update
Center lane closure on 200th St SW
As early as Monday, April 1, Sound Transit’s contractor will continue sewer work on 200th St SW. This will require the closure of the center lane on 200th St SW between 46th Ave W and 44th Ave W.…
Project update
Full closure of 46th Ave W
As early as Monday, March 25, Sound Transit’s contractor will continue working on potholing for existing utilities at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW.…
Project update
Center lane closure on 200th St SW
As early as Friday, March 22, Sound Transit’s contractor will continue signal work on 200th St SW. This will require the closure of the center lane on 200th St SW between 46th Ave W and 44th Ave W.…
Project update
Full closure of 48th Ave W
As early as Thursday, March 21, Sound Transit’s contractor will continue installing a storm crossing on 48th Ave W. This will require the full closure of 48th Ave W south of 200th St SW. Access to…
Project update
Full closure of 46th Ave W
As early as Monday, March 11, Sound Transit’s contractor will continue working on pavement markings at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW and the HOV ramp…
Project update
Full closure of 46th Ave W
As early as Monday, Feb. 26, Sound Transit’s contractor will continue working on pavement markings at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW and the HOV ramp…
Project update
Full closure of 48th Ave W
As early as Wednesday, Feb. 21, Sound Transit’s contractor will begin installing a storm crossing on 48th Ave W. This will require the full closure of 48th Ave W, south of 200th St SW. Access to…