Project update
Nightly closure of 44th Ave W
As early as Monday, April 15, Sound Transit’s contractor will perform road striping at 200th St SW and 44th Ave W as part of the Transit and Traffic Circulation Improvements Project. This work will…
Project update
Lane closures on 44th Ave W
As early as Monday, April 15, Sound Transit’s contractor will continue working on drainage installation, fiber tie-ins, and curb/gutter work on 44th Ave W. This will require crews to close the right-…
Project update
Lane closures on 46th Ave W
As early as Wednesday, April 10, Sound Transit’s contractor will begin activating the new traffic signal and removing the existing traffic signal on 46th Ave W and 200th St SW. This will require the…
Project update
Closure of the right lane/HOV lane of northbound I-5 on-ramp from NE 145th St
As early as Monday, April 8, Sound Transit will close the right lane/HOV lane of the northbound I-5 on-ramp from NE 145th St for landscaping. This work is part of the Lynnwood…
News release
Link 1 Line service to Lynnwood begins August 30
Sound Transit announced today that passenger service on the Link 1 Line will begin to Lynnwood on Aug. 30. The 8.5-mile segment will add four new stations: Shoreline South/148th St., Shoreline North/…
Project update
Closure of Alderwood Mall Blvd
As early as Friday, April 5, Sound Transit’s contractor will continue road work on Alderwood Mall Blvd. This will require the full closure of Alderwood Mall Blvd east of 44th Ave W. Detours will be…
Project update
Full daytime closure of 200th St SW
As early as Wednesday, April 3, Sound Transit’s contractor will continue road work on 200th St SW for mast arm installation for the traffic signals. This will require the full closure of 200th St SW…
Project update
Parking and paratransit/ADA drop-off opening at Lynnwood Transit Center
As early as Saturday, March 30, the parking lot south of the bus loop at the Lynnwood Transit Center will be open to the public for parking and paratransit/ADA drop-off. The bus layover area will be…
Project update
Center lane closure on 200th St SW
As early as Monday, April 1, Sound Transit’s contractor will continue sewer work on 200th St SW. This will require the closure of the center lane on 200th St SW between 46th Ave W and 44th Ave W.…
Project update
59th Place W parking and bus bay relocation
As early as Saturday, March 30, the parking lot and Bus Bay 1 at 59th Place W will be closed. The existing parking garage will remain open, and additional parking will be available at the park and…