Lynnwood Link Extension
Connecting Snohomish County with light rail

News and updates

Night work on the NE 175th St. to northbound I-5 on-ramp for pole installation

Starting as early as Wednesday, Jan. 18, Sound Transit will be installing poles at the NE 175th St. northbound I-5 on-ramp, requiring it to close during the night (due to lane and ramp closure…

NE 185th St. Lane Restriction for Concrete Pours

As early as Friday, Jan. 6, Sound Transit will restrict NE 185th St. down to one lane from 5th Ave NE to 8th Ave NE for concrete pours at the 185th undercrossing. During this daytime work, 8th Ave NE…

Northbound I-5 to NE 175th Street off-ramp closed for nighttime Track Equipment Mobilization work

On Saturday, Jan. 7, Sound Transit will close the northbound I-5 to NE 175th Street off-ramp and the northbound King County Metro on-ramp for the delivery of track equipment. A crane will be set up…

Nightly road closures of 1st Ave NE for potholing for utility work

As early as Wednesday, Jan. 4, Sound Transit will be performing road closures of 1st Avenue NE, from NE 103rd Street to Northgate Way NE, for potholing for utility work. As a result, the northbound I…

Nightly closure of I-5 Northbound Off-Ramp at NE 145th St.

As early as Wednesday, January 4, Sound Transit’s contractors will be working on the elevated guideway adjacent to NE 145th St. and I-5 in Shoreline. This work will require the closure of the…

NE 185th St. Lane Restriction for Concrete Pours

As early as Thursday, Dec. 30, Sound Transit will restrict NE 185th St. to one lane, from 5th Avenue NE to 8th Avenue NE, for concrete pours at the 185th St. undercrossing. 8th Ave NE, south of NE…

Nightly closure of I-5 NB off-ramp at NE 145th St

As early as Wednesday, Dec. 21, Sound Transit’s contractors will be working on the elevated guideway adjacent to the NE 145th St and I-5 in Shoreline. 

Night work coming soon to the Sound Transit Guideway between NE 182nd Court and NE 185th Street

Starting Monday, Dec. 19, Sound Transit will be performing night work inside the guideway along 5th Ave NE between NE 182nd Ct. and NE 185th St. We’re working to build noise and retaining walls that…

Lynnwood Link opening timeframe update

The Sound Transit Board System Expansion Committee today received a briefing on the continuing work to reliably set new opening dates for our extensions to the Eastside, Lynnwood and Federal Way.

Updated work dates: Night work coming soon to the Shoreline Fire Department Station Driveway

As early as Monday, Dec. 5, contractors will be performing night work along the Sound Transit guideway at the Shoreline Fire Department Station 65 driveway as part of the Light Rail Lynnwood Link…