Project update
Overnight closure of off-ramp to westbound State Route 104 and off-ramp to SR 104 eastbound
On Sunday, March 7, Sound Transit’s contractor will work overnight at the State Route (SR) 104 and NB I-5 interchange. All lanes of traffic on SR 104, the off-ramp from I-5 NB to SR 104 WB, and the…
Project update
Night closure at 1st Ave NE Northgate Way intersection and NB I-5 Northgate Way on-ramp for guideway construction
As early as Thursday, March 4, Sound Transit will be closing 1st Avenue Northeast and Northgate Way intersection and the Interstate 5 northbound on-ramp at Northgate Way. The nighttime closure will…
Project update
Nighttime closure at NE 130th off-ramp from northbound I-5 for guideway work
As early as Thursday, March 4, Sound Transit will close the off-ramp at Northeast 130th Street going northbound of Interstate 5 for night work. This closure will be utilized for guideway work for the…
![Workers dwarfed by the elevated tracks heading into Mountlake Terrace Station.](/sites/default/files/styles/post_thumbnail/public/2021-02/mountlake-terrace-station1.jpg?h=10d202d3&itok=uTUeWJ0d)
The Platform
Fresh pics: Lynnwood Link construction going strong
You can't miss light rail construction stretching into Snohomish County as the Lynnwood Link light rail extension rises next to I-5. Look on both sides of the interstate for crews busy…
Project update
Road closure on 1st Ave between NE 158th to NE 159th for storm work
On Wednesday, February 24th, Sound Transit will be closing 1st Ave NE to work on storm drains. The closure will take place between the work hours of 7:00a.m to 5:00p.m. What Work consists of…
Project update
Night closure of off-ramp to westbound SR 104 and off-ramp to eastbound SR 104
On Monday, Feb. 22, Sound Transit's contractor will work at night at the State Route (SR) 104 and northbound Interstate 5 interchange. All lanes of traffic on SR 104, the off-ramp from I-5 northbound…
Project update
Night closure at 1st Ave NE from NE 112th to NE 113th Street
As early as Monday, Feb. 22nd, Sound Transit will be closing 1st Avenue Northeast from Northeast 112th Street to Northeast 113th Street. The full night time closure will be utilized to for deck work…
Project update
Night closure at Northeast 107th northbound I-5 on-ramp and on off-ramp
As early as Monday, Feb. 22nd, Sound Transit will close the Northeast 107 on-ramp to northbound Interstate 5 and the off-ramp. The full night time closure will be utilize for deck work. What…
Project update
60th Ave West closed for night work and girder placement
As early as Tuesday, February 16, Sound Transit’s contractor will continue to deliver and set girders along 60th Ave W for the Lynnwood Link Extension trackway. There will also be a road closure of…
Project update
Closure of Interurban Trail for Lynnwood Link Extension
As early as Monday, February 15, Sound Transit’s contractor will be working along the Interurban Trail adjacent to the Edmonds School District Bus yard. The Interurban Trail will be closed while this…