Project update
60th Ave West closed for night work and girder placement
As early as Tuesday, February 16, Sound Transit’s contractor will continue to deliver and set girders along 60th Ave W for the Lynnwood Link Extension trackway. There will also be a road closure of…
Project update
Closure of Interurban Trail for Lynnwood Link Extension
As early as Monday, February 15, Sound Transit’s contractor will be working along the Interurban Trail adjacent to the Edmonds School District Bus yard. The Interurban Trail will be closed while this…
Project update
Right lane closures at NE 175th and off-ramp from Northbound I-5
Tuesday, February 9th, Sound Transit will be closing both right lanes towards the on-ramp to Northbound I-5 and additionally the NB I-5 off-ramp closure at NE 175th Street. The closure will be…
Project update
Night work traffic shifts on Northeast 155th Street near the fire station between 1st Ave NE to 2nd Ave NE
As early as Wednesday, February 10th, Seattle City Light will be working on NE 155th of Interstate-5 underpass. This work is part of Sound Transit's Lynnwood Link Extension Project to work on the…
Project update
Off-ramp closure at Northbound Interstate-5 Northeast 145th Street exit 175
As early as Monday, February 8th, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 to work on removing light bases. This closure is a necessary step for construction of the…
Project update
236th St SW eastbound closure
As early as Monday, February 8, Sound Transit’s contractor will begin work to install girders for the Lynnwood Link Extension trackway. The work area is located on 236th St SW in front of the…
Project update
Opening of the Mountlake Terrace parking lot at 59th Place and new bus loop
On Sunday, March 7, Sound Transit’s contractor will open the parking lot at 59th Place off 236th St SW. This parking lot is located on the eastern half of the MLT Transit Center. The new bus loop is…
Project update
Right lane closure and off-ramp closure at northbound I-5 NE 145th Street, exit 175
As early as Monday, Feb. 1st, Sound Transit will be closing two right lanes on Interstate 5 north from Northeast 128th to Northeast 145th. Additionally, the off-ramp from northbound I-5 via exit 175…
Project update
46th Ave W/HOV ramps to Lynnwood Transit Center closed for one night
As early as Monday, Feb. 1, Sound Transit's Sound Transit's contractor will be closing the 46th Avenue West HOV ramps to the Lynnwood Transit Center. These ramps will be closed for one night to pour…
Project update
Night closure at I-5 northbound Northgate Way on-ramp for heavy equipment mobilization
On Monday, February 1st, Sound Transit will be closing I-5 Northbound on-ramp at Northgate Way. The night time closure will be utilized to continue deck work for the future light rail guideway. This…