Project update
Traffic changes at NE 185th undercrossing at NE 185th Street and 5th Ave near Shoreline Stadium
Starting Monday, November 22nd, Sound Transit’s contractors will begin making traffic changes at the NE 185th and 5th undercrossing near Shoreline Stadium.
Project update
Night work along the I-5 and State Route 104 Interchange
Tuesday, November 9, Sound Transit’s contractor will work at night along the I-5 and the SR 104 Interchange in Shoreline to complete a concrete pour for the elevated guideway for the future Lynnwood…
Project update
Cancelled: One lane road with alternating traffic on Northeast 155th Street between 1st Ave NE to 2nd Ave NE
*The extended work on NE 155th St. which was scheduled to occur from Monday 11/8 – Thursday 11/11 is postponed for a future date which has yet to be determined.
Project update
Night time full closure at NE 155th Street from 1st Ave to 5th Ave
As early as October 18th, Sound Transit will begin a full closure at NE 155th Street for girder delivery and guideway work.
Project update
Night work along the I-5 and State Route 104 Interchange
As early as Monday, October 18, Sound Transit’s contractor will begin a night operation along the I-5 and the SR 104 Interchange in Shoreline to complete concrete pours for the elevated guideway for…
Project update
Rescheduled work: Alternating lane closure at NE 185th Street and 5th Ave overcrossing
This work has been rescheduled to Oct. 19th. Sound Transit will be alternating lane closure at Northeast 185th Street and 5th Avenue for pothole work.
Project update
Extended full closure at NE 145th overcrossing and NB I-5 NE 145th Street exit 175
This work will be extended to October 14th. Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for work zone for girder setting. Additionally, there will be a full closure at the NE…
Project update
189th St and 8th Ave Utility Construction
Sound Transit construction efforts continue to move forward. Construction crews are currently making their approach to the intersection of 189th St. and 8th Ave. and will begin to move into Phase 3…
Project update
Night work along the I-5 and State Route 104 Interchange Sept. 29 and 30
Wednesday, September 29 and Thursday, September 30, Sound Transit’s contractor will work at night along the I-5 and the SR 104 Interchange in Shoreline to complete concrete pours for the Lynnwood…
Project update
Nightly full road closures of NE 175th Street
Starting Monday, September 20th, Sound Transit will be closing both directions of NE 175th Street from 5th Ave NE to the I-5 overpass. Additionally, both NE 175th Street to Northbound I-5 on &…