Project update
Night closure of northbound I-5 on-ramp, left lanes, and off-ramp
On Saturday, Dec. 16, Sound Transit will close the northbound I-5 on-ramp at NE 175th Street, the northbound I-5 left lanes between NE 155th St and NE 195th St, and the northbound I-5 off-ramp to SR-…
Project update
Night closure of northbound I-5 on-ramp and left lanes
On Saturday, Dec. 2, Sound Transit will close the northbound I-5 on-ramp at NE 175th St. and the northbound I-5 left lanes between NE 155th St. and NE 195th St. for a striping refresh. This work is…
Project update
Extended road closure for curb and roadway restoration at 1st Ave NE and NE 174th St
As early as Monday, Oct. 2, Sound Transit will be performing curb and roadway restoration on 1st Ave NE from NE 170th St. to NE 174th St. …
Project update
NE 161st St. restoration and Ridgecrest Park parking lot closure
Starting as early as Monday, Oct. 2, Sound Transit will be closing the west end of NE 161st St. for road restoration. As a result, the driveway to the …
Project update
Closure of the northbound King County Metro North Base Off and On-Ramp
As early as Monday, Sept. 18, Sound Transit will be closing the northbound I-5 King County Metro off-ramp for two weeks and the on-ramp for six weeks. This work is for curb restoration and noise wall…
Project update
NE 185th Street restoration work
As early as Monday, Aug. 28, Sound Transit will be closing 8th Ave NE, both north and south of NE 185th Street, as part of the new NE 185th Street road alignment. The work includes an updated roadway…
Project update
Nightly closures at SR 104 Interchange
updated 8/17/2023 As early as Thursday, August 17, Sound Transit’s contractor will extend their work at the SR 104 interchange in Shoreline for guardrail installation and barrier removal. This work…
Project update
Early morning construction to start in and around the NE 185th St. Station/Garage
Starting as early as Saturday, July 29, contractors will start early morning work as a part of the Lynnwood Link Extension project. This will consist of site grading at NE 185th Street, from 5th…
Project update
Night closures at SR 104 Interchange
As early as Monday, July 24, Sound Transit’s contractor will work at the SR 104 Interchange in Shoreline for drainage structure installation, excavation, and traffic barrier shifting as necessary.…
Project update
Night closure of right lane on westbound NE 175th St.
As early as Monday, July 17, Sound Transit will be performing a westbound right lane closure of NE 175th St. between the northbound I-5 on- and off-ramps and 3rd Ave NE. We’ll be fixing potholes as…