Project update
Intersection closure of Northeast 20th Street at 136th Place Northeast beginning as early as Dec. 3
Beginning as early as Monday, December 3 and lasting through the morning of Friday, December 14, Sound Transit contractor crews will close the intersection of Northeast 20th Street at 136th Place…
Project update
Rail Delivery Begins at Judkins Park
Rail will begin arriving at the Judkins Park Station site as early as Thursday November 29. Deliveries will occur overnight, from 8 p.m. to 4 a.m. To safely complete this work, crews will close the…
Project update
Construction update: Upcoming construction traffic impacts Monday, Nov. 26 – Tuesday, Jan. 1
I-90 In order to safely construct East Link's aerial guideway in south Bellevue, Sound Transit is planning the following closures: Monday-Thursday (Friday morning) night closures, 8 p.m. to 5 a.m…
Project update
Construction alert: Rescheduled night closures on I-405 in Bellevue on Nov 20th
Due to resource availability in proximity to the upcoming Thanksgiving holiday, the scheduled lane closures on I-405 on Nov. 20th have been delayed. Sound Transit's contractor will resume concrete…
Project update
Join the East Link Facebook Group
Are you a Facebook user? Would you like to stay informed about the latest construction progress, see cool photos and engage with the project’s community outreach team? If so, you can join our new…
Project update
Take a survey about the Eastside Rail Corridor
Did you know that the Eastside Rail Corridor (ERC) runs more than 25 miles through King County? The former railway turned multi-purpose corridor connects the cities of Renton, Bellevue, Kirkland,…
Project update
Night closures on I-405 in Bellevue on Nov 19th – 20th
Overnight drivers should be aware of upcoming closures on Interstate 405 in downtown Bellevue. Beginning Monday, November 19th, Sound Transit’s contractor will continue concrete pours of horizontal…
The Platform
East Link light rail line already transforming Eastside skyline
Our latest photo update on progress building new light rail lines connecting the region takes us to the East Link extension – 14 miles of new light rail with ten stations connecting Seattle, Mercer…
News release
Light rail guideway soon to cross I-90 in south Bellevue
Construction method uses specialized cranes that enable the bridge to be built over the freeway with minimal disruption to traffic Sound Transit today briefed media on East Link light rail guideway…
Project update
Ramp and lane closures between I-90 and Bellevue Way Southeast
Crews working to build Sound Transit's East Link project in south Bellevue continue installation of precast concrete girders during the week of Nov. 12. Ramp and lane closures will be necessary to…