80th Avenue HOV I-90 on-ramp closure
Sound Transit's contractor will close the 80th Avenue Eastbound HOV I-90 on-ramp to shift barriers to prepare for Mercer Island station construction. This closure is planned for 9 p.m. to 1 a.m.…
Project update
Upcoming Bellevue Way Southeast partial weekend closure and construction traffic impacts in south Bellevue
Weekend of Aug. 19-20 Bellevue Way Southeast reduced to one lane and ramps to I-90 closed Utility relocation work will continue this weekend on Bellevue Way Southeast. Sound Transit's contractor…
Project update
SR 520 nighttime lane/ramp closures planned for tree removal near Overlake Transit Center
Construction crews working to build the East Link light rail extension plan to remove trees at night along eastbound SR 520 in Redmond. The work is scheduled from 10 p.m. to 5 a.m. nightly Wednesday…
Project update
New Park-and-Ride option in South Bellevue – served by ST Route 550
A new temporary park-and-ride lot has been opened in south Bellevue. The new lot located at 1624 Bellevue Way SE, provides parking for up to fifty vehicles and includes four signed 15-minute parking…
Project update
Construction alert: South Bellevue
In this alert: Upcoming Bellevue Way SE weekend closure; construction traffic impacts in south Bellevue; tree removal related to soil stabilization work along 112th Ave SE and Winters House…
Project update
In this alert: Soil stabilization work along 112th Ave SE and construction traffic impacts in south Bellevue
Soil stabilization activities Work to stabilize soil along 112th Avenue Southeast is underway. Sound Transit's contractor will install temporary steel sheet piles, construct an embankment surcharge…
Project update
Lane and sidewalk closure on NE 20th St. in Bellevue
Beginning on Thursday, Aug. 3 and lasting for approximately one week, Sound Transit's contractor plans to close the far right lane of eastbound Northeast 20th Street, near the intersection of 136th…
Project update
Thank you for attending the Mercer Island construction open house
Thank you to all who attended our Mercer Island construction kick off open house on July 12. We were thrilled with the turnout and thoughtful conversations. If you weren't able to attend in-person,…
Project update
Changes coming to Overlake Transit Center
To make room for construction of the future Redmond Technology Center light rail station and parking garage, crews need to shift the Overlake Transit Center services to the southeast part of the site…
Project update
Temporary parking lot to open for Mercer Slough Park users
On July 31st, the parking lots at the Winters House and Blueberry Farm will close for East Link construction. Access to Mercer Slough Park and the trail system will remain open. During the closure,…