Link light rail alert
Announcement Ongoing

Shoreline South/148th Station will have scheduled maintenance beginning Monday, Dec 2 through Friday, Dec 6. The work will take place from 7 a.m. to 3 p.m. daily, however pedestrian access in the area will be restricted.

In effect: Dec. 2-6

Routes: 1 Line
The scheduled maintenance is to adjust handrails at 2 accessible ramps and 1 stairwell at the entrance to the 148th station/garage.

The work will occur in 3 phases.

Phase 1: Dec 2-4
The ramp on the south side of the entrance will be closed (stairs on south side and ramp on north side of entrance to remain open).

Phase 2: Dec 4-5
The stairs will be closed (ramps on side and north side of entrance remain open).

Phase 3: Dec 5-6
The ramp on the north side of the entrance/148th will be closed (ramp and stairs on south side of entrance remain open).

Work will be done sequentially, so there is always one ramp at the entrance open. The accessible path on the south side of the garage will remain open.

The maintenance is weather dependent, dates and times are subject to change.