Project update
UPDATE – Nighttime closures of 136th Pl NE to begin later this fall
Nighttime work involving road closures and excavation across 136th Pl NE has been postponed until later this fall to better align with other related work activities. Additional updates will be…
Project update
Drilled shaft work begins in downtown Bellevue
This week, Sound Transit’s contractor began drilling shafts in downtown Bellevue to support construction of the elevated guideway. Typical…
Project update
Off-peak daily Island Crest Way westbound HOV ramp closures
Beginning as early as Tuesday, September 5 and lasting until Monday, September 18, the Island Crest Way westbound HOV on-ramp will close daily during off-peak daytime hours to minimize traffic…
Project update
Weekend Sept. 2-4: No weekend closures planned for Bellevue Way SE
Bellevue Way Southeast will remain open during Labor Day Weekend. Week of Sept. 5 – Sept. 8 Tuesday-Friday 10 a.m. to 8 p.m.: As needed, one northbound lane of Bellevue Way Southeast may be closed…
Project update
UPDATE – Nightly Island Crest Way westbound HOV ramp closures postponed
The nightly closures of Island Crest Way westbound HOV on-ramp originally scheduled to begin Monday, Aug. 28, have been postponed to a future date. Sound Transit will notify community members once…
Project update
Nightly Island Crest Way westbound HOV ramp closures
Beginning as early as Monday, Aug. 28 until Monday, Sept. 11, the Island Crest Way westbound HOV on-ramp will close nightly between 9.p.m. and 5 a.m. Sound Transit's contractor will use these…
Project update
Intersection Closure of 132nd Avenue NE and NE Spring Blvd. in Bellevue
Beginning on Monday, August 28 and lasting for approximately two weeks, Sound Transit’s contractor will be working in the intersection of 132nd Avenue NE and NE Spring Blvd in BelRed. There will be…
Project update
East Link work begins near Lakeside Avenue South
Crews working for Sound Transit will begin work to seismically retrofit the I-90 bridge columns near Lakeside Avenue to prepare for light rail construction and operation. Beginning as early as Aug.…
Project update
No weekend closures planned for Bellevue Way SE
Weekend Aug. 26-27 Bellevue Way Southeast will remain open during the weekend of Aug. 26-27 and Sept. 2-4 (Labor Day Weekend). Week of Aug. 28 – Sept. 1 Monday- Friday 10 a.m. to 8 p.m.: As needed…
Project update
Clearing and grubbing along 112th Avenue SE at Surrey Downs Park
Starting Tuesday, Aug. 22, Sound Transit's contractor will begin to clear and grub along Sound Transit owned parcel (see map) along 112th Avenue Southeast and within the southeast corner of Surrey…