Link light rail alert
Announcement Upcoming

Beginning March 24 through May 30 construction activity will take place at Pinehurst Station.

In effect: March 24 - April 14

Routes: 1 Line
Construction will take place at the new Pinehurst Station. Trains will share one track through the Shoreline South/148th Station requiring passengers to use the alternate side of the platform during construction hours. Work will take place evenings, Monday through Friday, from 7 p.m. until the end of light rail service, and all day on Saturday and Sunday. Trains will arrive about every 12 minutes during construction.

Phase 1: March 24 through April 13 - Trains will be using the Lynnwood platform.

Phase 2: April 28 through May 30 - Trains will be using the Angle Lake platform.

No work will be done May 17 - 18, and during the Memorial Day weekend of May 24-26